Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 02, 2017 6:55 am

Natick Plaza pad is poured, all the conduit is done, and bollards.

IMG_6323.JPG


Donald says:

"The contractor is returning today to complete the sidewalk work. We are waiting on a date from the utility to tie into the transformer. We are hopeful for a week or two."
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2598
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Wed Feb 22, 2017 4:55 pm

Sidewalk and conduits look good. Weather is so nice, you could almost plant grass. Control panels look half done. Charger still in the crate. Couple more weeks?

IMG_6371.JPG


IMG_6370.JPG
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2598
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 23, 2017 6:47 am

DOT replies:

We lost a little ground in Natick and Framingham due to snow storms, but we should be able to get started next week and avoid some potential weather mid-week. We heard from the utility last week that we are on their radar to replace transformers in the next 3-4 weeks. We are hoping we can get both stations completed at the same time.

We also heard back from utility on the Charlton sites, they are ready to approve our work/service requests and trench design so we may be able to move on to those sites once Framingham and Natick are completed.



So, I'm guessing end of March for Natick and Framingham and maybe Memorial Day for Charlton.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2598
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 23, 2017 10:12 am

Wow, one of the DOER units just got posted to Plugshare. Thought they'd take longer.

IMG_6374.JPG
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

Return to “Eastern USA”