Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 02, 2017 6:55 am

Natick Plaza pad is poured, all the conduit is done, and bollards.

IMG_6323.JPG


Donald says:

"The contractor is returning today to complete the sidewalk work. We are waiting on a date from the utility to tie into the transformer. We are hopeful for a week or two."
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Wed Feb 22, 2017 4:55 pm

Sidewalk and conduits look good. Weather is so nice, you could almost plant grass. Control panels look half done. Charger still in the crate. Couple more weeks?

IMG_6371.JPG


IMG_6370.JPG
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 23, 2017 6:47 am

DOT replies:

We lost a little ground in Natick and Framingham due to snow storms, but we should be able to get started next week and avoid some potential weather mid-week. We heard from the utility last week that we are on their radar to replace transformers in the next 3-4 weeks. We are hoping we can get both stations completed at the same time.

We also heard back from utility on the Charlton sites, they are ready to approve our work/service requests and trench design so we may be able to move on to those sites once Framingham and Natick are completed.



So, I'm guessing end of March for Natick and Framingham and maybe Memorial Day for Charlton.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Feb 23, 2017 10:12 am

Wow, one of the DOER units just got posted to Plugshare. Thought they'd take longer.

IMG_6374.JPG
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

Foschas
Posts: 57
Joined: Thu Jul 30, 2015 6:35 pm
Delivery Date: 31 Jul 2015
Leaf Number: 320277
Location: Mass

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Thu Jun 01, 2017 4:57 am

Anyone have updates on the Mass Pike quick chargers? Planning a trip out west and can't find any info online.

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Mon Jun 05, 2017 5:57 am

Natick is in, you can see it on plugshare, but don't know if it's on yet. Framingham should be in by now, but haven't checked on it yet.
Both sides of Charlton will come later this year. Takes them forever.
Lee Plazas may be in progress, haven't asked lately and too far for me to comfortably check.
All the other Plazas are just future plans.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Mon Jun 05, 2017 7:49 am

The eVgo at DD in Riverside, just over the river is your best bet for now.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

NeilBlanchard
Posts: 565
Joined: Sat Oct 11, 2014 5:02 pm
Delivery Date: 14 Oct 2014
Leaf Number: 306278

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Mon Jun 05, 2017 11:22 am

When I get my EVgo card, I will try to check out some of these. Plugshare still shows the Natick station as "coming soon".

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Mon Jun 05, 2017 1:40 pm

Donald Petty at the DOT told me they'd be free for a short while, but they'll probably still need a card. No news yet on how they plan to set fees.

They were having trouble trying to connect a new transformer at Natick, but it's dragged on so long now, I won't be surprised if it takes another month.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

User avatar
DNAinaGoodWay
Gold Member
Posts: 2645
Joined: Mon Dec 17, 2012 1:43 am
Delivery Date: 03 Dec 2012
Leaf Number: 23156
Location: Central Massachusetts

Re: MA Clean Vehicle Project - $50k QC Deployment Awards

Tue Jun 06, 2017 8:36 am

Natick, this morning:

IMG_6672.JPG


IMG_6671.JPG


So, not yet. Hope they have some signs. High risk of ICEing.
You do not have the required permissions to view the files attached to this post.
'12 SL last reading @ 2 yr, 22k, 260 GIDs, 62.35 Ahr

'15 SV w/QC, Mfd 5/14, Leased 8/14, 292 GIDs, 64.38 Ahr when new

@ 25 months, 25k, 267 GID, 56.88 Ahr
@ 29 months, 29k, 286 GID, 60.88 Ahr
@ 31 months, 30.3k, 274 GID, 58.39 Ahr

6.72 kW Array

Return to “Eastern USA”