We lost a little ground in Natick and Framingham due to snow storms, but we should be able to get started next week and avoid some potential weather mid-week. We heard from the utility last week that we are on their radar to replace transformers in the next 3-4 weeks. We are hoping we can get both stations completed at the same time.
We also heard back from utility on the Charlton sites, they are ready to approve our work/service requests and trench design so we may be able to move on to those sites once Framingham and Natick are completed.
Once the station is commissioned (any day now according to utility) we will be installing the restricted parking signs.