PG&E processing Solar Interconnection Agreements

My Nissan Leaf Forum

Help Support My Nissan Leaf Forum:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.
PG&E keeps "forgetting". You should have the phone number of the contact person assigned to your case.

You have to keep calling that person.

I called mine to see what happened to my app. They wanted me to change one detail bit. Re-sent. Nothing happened. Called one week later, they don't have it. Re-sent via email this time. Got it. Nothing happened for a week. Called again. Approved this time. Will send someone to inspect/change meter. This happened fast, within 3 days. Got a tag saying you're good to go. Turned on my solar. Waited many weeks later before first statement came in. Doesn't say I'm on E6 like I applied for. Called again, response "You should be, that's what you applied for" but I said "there's nowhere in my bill or online that says I'm on E6". Told me to wait for the next statement. Grrr.
 
I was able to get mine processed quickly by filing a complaint with the CPUC.

:D

There is a 150 page 'law' of how the interconnections are to be handled. They have 30 days to process the agreements of the 'small' providers like us (rooftop solar, wind, etc.). Without a complete reading, nor being able to digest it all, my takeaway is:

1. PG&E must contact you within 10 days in WRITING if there is a problem with processing your application.

2. If your application is resubmitted, the 30 day countdown clock starts at the beginning again.

So, my takeaway is that PG&E is working to have us resubmit the applications so that they can avoid crediting us for solar, and they can follow the 'law'.

I would be happy to share my complete story and the names of the people at PG&E that 'worked' on my application.... I hope the CPUC asks me. ;)


Edit: note that the on-line CPUC complaint form does not trigger an email with your case number. They will mail it to you via postal service.
 
Hello,

I'm a journalist with NBC Bay Area News and I'd like to talk to you about the solar interconnection process with PG&E. Would you please email me at [email protected]? Thank you.

Best,

Liz Wagner
nbcbayarea.com/investigations
 
Question4You said:
Hello,

I'm a journalist with NBC Bay Area News and I'd like to talk to you about the solar interconnection process with PG&E. Would you please email me at [email protected]? Thank you.

Best,

Liz Wagner
nbcbayarea.com/investigations

I'm not in California but thanks for taking up this issue!
 
I have solar installed in the PGE territory and I had no problem. Maybe its because the solar installer helped with the paperwork. Because of the billing cycle it took about a month to see the changes on my electric bill.
 