From the DOT:
I will verify payment process tomorrow. It is my understanding that until we implement a fee there will be no cards required. Simply press screen options.
Framingham - Still work required by utility. Station activation may be sometime in mid to late July.
Lee West- Station installed. Activation should occur in the next 2 weeks. Waiting on utility.
Lee East- Still some site work required. Should be active in 3-4 weeks.
Charlton East- Still coordinating work with utilities, activation may be late July, early August.
Charlton West- Utility work should be scheduled in the next two weeks, activation mid to late July.
Multiple units per site is still up in the air. We hope that the VW settlement will provide those resources. Sites already have the service capacity, conduit, and designs to accept at least two additional stations.