danrjones
Posts: 1136
Joined: Wed Apr 17, 2019 8:02 am
Delivery Date: 17 Jun 2019
Location: Ridgecrest, CA

Re: Update on CalTrans District 9 (Sierra Nevada East Side) DC Fast Charger Program

Tue Jun 29, 2021 9:19 am

paulgipe wrote:
Sun Jun 27, 2021 3:24 pm
Guy,
Yeah, they're all up and running. Single units, 50 kW, but they've been working and people have been using them. We hope to get up the East Side in August. We're still exploring the Kern Plateau and we can do that from Bako.
Paul
One thing I have noticed is that someone is labeling the Caltrans units as 100 kW on plugshare, but obviously they are not. I'm not sure why that is occurring.
2018 Leaf SV Pearl White with Tech and All Weather, Purchased New on 5/3/19

User avatar
paulgipe
Posts: 398
Joined: Sat Aug 02, 2014 4:23 pm
Delivery Date: 20 Oct 2014
Leaf Number: 311200
Location: Bakersfield, CA 93305
Contact: Website

Re: Update on CalTrans District 9 (Sierra Nevada East Side) DC Fast Charger Program

Tue Jun 29, 2021 2:43 pm

danrjones wrote:
Tue Jun 29, 2021 9:19 am
paulgipe wrote:
Sun Jun 27, 2021 3:24 pm
Guy,
Yeah, they're all up and running. Single units, 50 kW, but they've been working and people have been using them. We hope to get up the East Side in August. We're still exploring the Kern Plateau and we can do that from Bako.
Paul
One thing I have noticed is that someone is labeling the Caltrans units as 100 kW on plugshare, but obviously they are not. I'm not sure why that is occurring.
They're 100 Amp, not 100 kW. The Caltrans person who uploaded the data got it wrong and hasn't bothered to correct it. To my knowledge we can correct it ourselves but editing it on PlugShare. Then PlugShare will update the listing. Can you try one or all of them Dan? I've done it before for other stations.

Paul
Bakersfield, California
2017 Bolt LT with DCFC, leased 11/09/17
2015 Nissan S with QC, leased, returned
2013 Chevy Volt Premium, used 10/3/16, sold
http://www.wind-works.org

danrjones
Posts: 1136
Joined: Wed Apr 17, 2019 8:02 am
Delivery Date: 17 Jun 2019
Location: Ridgecrest, CA

Re: Update on CalTrans District 9 (Sierra Nevada East Side) DC Fast Charger Program

Wed Jun 30, 2021 6:41 am

paulgipe wrote:
Tue Jun 29, 2021 2:43 pm
danrjones wrote:
Tue Jun 29, 2021 9:19 am
paulgipe wrote:
Sun Jun 27, 2021 3:24 pm
Guy,
Yeah, they're all up and running. Single units, 50 kW, but they've been working and people have been using them. We hope to get up the East Side in August. We're still exploring the Kern Plateau and we can do that from Bako.
Paul
One thing I have noticed is that someone is labeling the Caltrans units as 100 kW on plugshare, but obviously they are not. I'm not sure why that is occurring.
They're 100 Amp, not 100 kW. The Caltrans person who uploaded the data got it wrong and hasn't bothered to correct it. To my knowledge we can correct it ourselves but editing it on PlugShare. Then PlugShare will update the listing. Can you try one or all of them Dan? I've done it before for other stations.

Paul
Sure, can do.
2018 Leaf SV Pearl White with Tech and All Weather, Purchased New on 5/3/19

User avatar
paulgipe
Posts: 398
Joined: Sat Aug 02, 2014 4:23 pm
Delivery Date: 20 Oct 2014
Leaf Number: 311200
Location: Bakersfield, CA 93305
Contact: Website

Re: Update on CalTrans District 9 (Sierra Nevada East Side) DC Fast Charger Program

Fri Jul 02, 2021 3:46 pm

I just tried to edit the one in Bakersfield. PlugShare has changed the process but I sent in a "remark."

Paul
Bakersfield, California
2017 Bolt LT with DCFC, leased 11/09/17
2015 Nissan S with QC, leased, returned
2013 Chevy Volt Premium, used 10/3/16, sold
http://www.wind-works.org