It's end of November now, and I haven't seen Public Charger #1 installed in San Diego.
To get 1,450 "Publicly Available Level 2 EV chargers" installed "Nov through June 2011", they're going to be busting up a lot of concrete in the next seven months!
That works out to about nine new chargers per weekday. We're 27 days into the installation window now, and I'm not seeing any activity. Anyone?
I'm not savvy in the ways of planning, permitting, and electrical construction, but this seems like a ludicrously aggressive plan.
Is EVProject capable of doing it, or is this all a funding ploy ready-made for overruns and delays?
I'm concerned that a general failure of EVProject to make good on the infrastructure could leave the early-2011 deliveries with more home charging than I was hoping for.
To get 1,450 "Publicly Available Level 2 EV chargers" installed "Nov through June 2011", they're going to be busting up a lot of concrete in the next seven months!
That works out to about nine new chargers per weekday. We're 27 days into the installation window now, and I'm not seeing any activity. Anyone?
I'm not savvy in the ways of planning, permitting, and electrical construction, but this seems like a ludicrously aggressive plan.
Is EVProject capable of doing it, or is this all a funding ploy ready-made for overruns and delays?
I'm concerned that a general failure of EVProject to make good on the infrastructure could leave the early-2011 deliveries with more home charging than I was hoping for.